Net Requirements, Not Grossuse stock and planned receipts before buying or making more
Every Requirement Has an Originevery proposal traces back to the order or forecast behind it
Order on Time, Not Earlywork back from the requirement date, not forward from today
Material and Capacity in One Runcheck resource load in the same scenario as material
Recommend, Then DecideMRP proposes; the planner decides what becomes a request
The Five Concepts
From net requirements to decisions you own
Two stages. How the requirement is calculated: net requirements, origins and dates. Checking and acting on it: resource load and the planner's decision.
01
How the requirement is calculatedConcept 01 · Use stock and planned receipts before buying or making more
Net Requirements, Not Gross
The shop-floor problem it solves
The plant buys or makes again what is already on the shelf or already on order, and cash sits in duplicate stock.
The concept explained
MRP always breaks down assembly requirements, for example from a customer order, through the bill of materials. When a component is a stock-related sub-assembly, Beas first checks whether stock or planned inflow can cover it, and reserves that cover temporarily for the requirement. Only the part that stays uncovered is broken down further. This is the requirement coverage calculation. With Coverage calculation priority set to By Documents, it follows this priority: minimum inventory first, then the production outflow of work orders and planned orders, then customer orders, advance invoices and forecasts set “like customer order”, then transfer requests, then other forecasts. Breakdown replenishment sets which inflows count. With every option on, the breakdown is net; with none, it is gross, and the stock of the sub-assembly no longer reduces the material requirement.
Everyday analogy
Before writing the weekly grocery list, you check the kitchen shelf and what is already ordered from the kirana store. Only what is still missing goes on the list, and nobody comes home with a second bag of rice.
Where it lives in Beas
MRP > MRP Wizard > Open > Detail tab > Breakdown replenishment holds Consider goods receipt from production, Include warehouse stock, Consider goods receipt from PO and Consider multiple orders. Coverage calculation priority (By Documents or By Date) sits under Pegging and replenishment > Computation type. After a run, Order recommendation > Origin shows the temporary reservations.
Swipe sideways to see the full diagramIllustrative figures: net breakdown uses the stock of the sub-assembly first, so less material is required.
02
How the requirement is calculatedConcept 02 · Every proposal traces back to the order or forecast behind it
Every Requirement Has an Origin
The shop-floor problem it solves
A purchase is proposed and nobody can say which order or forecast caused it, so the list is second-guessed line by line.
The concept explained
In Beas, the originator of a requirement is its pegging, such as a customer order, a work order, a forecast or minimum inventory. When MRP breaks an assembly down, the requirements it creates below can be traced back to the pegging that caused them. After the calculation, the Origin of Requirement structure shows which pegging caused which requirement, from which peggings a requirement arose and which inflow covers it, including temporary reservations. How much of that link survives depends on Sum peggings. With Detail, every pegging is shown separately, which suits order-related purchases and high-value goods. Summarising by day, week or month calculates faster with large data volumes, but the reference to the pegging is lost.
Everyday analogy
A household list where every line says who it is for: notebooks for the school project, extra rice for Sunday's guests. Write only “monthly shopping” and nobody can later say why there are twelve notebooks in the cupboard.
Where it lives in Beas
In the Order recommendation, right-click in the inflow and outflow tab and choose Origin to open the Origin of Requirement structure. Sum peggings sits in Detail tab > Pegging and replenishment > Computation type. Items outside the Scheduling tab filters are not saved, and their links cannot be shown.
Swipe sideways to see the full diagramEvery requirement traces back to its pegging, unless peggings are summarised.
03
How the requirement is calculatedConcept 03 · Work back from the requirement date, not forward from today
Order on Time, Not Early
The shop-floor problem it solves
Material arrives weeks too early and ties up cash, or a day too late and the line stops.
The concept explained
Every requirement carries a date: the delivery date of a customer order, the planned date of a forecast, or, for a work order component linked to a routing position, the start of that operation (with Consider link to operations on). MRP works back from that date. For customer orders the average delivery time is subtracted first; then the lead time and buffer days, and for purchased parts the goods receipt idle time as well. That is why the order proposal date is not the requirement date. For assemblies, Calculate lead time for assembly runs a backward scheduling simulation over the routing to find the latest possible start; existing capacities and time reservations are not considered. For sub-assemblies it applies only to order-related ones; storage-related sub-assemblies keep the fixed lead time from the item master. If the result lies in the past, the proposal moves to the next working day.
Everyday analogy
Booking a gas cylinder refill. Delivery takes a few days, so you book when a few days of gas are left, not the week the last cylinder arrived and not on the evening it runs out.
Where it lives in Beas
Lead time sits in Item master > Master Data tab > Planning data, in work days; a lead time of 0 is flagged as an error by the data check. Calculate lead time for assembly sits in Detail tab > Pegging and replenishment > Computation type. Average lead time, Lead time assurance and Goods receipt PO idle time in workdays (Purchased items) sit in Administration > System Initialization > Configuration Wizard > Materials management > MRP Wizard > Calculation.
Swipe sideways to see the full diagramFor customer orders the average delivery time comes off first, then lead time and buffer days; a date in the past moves to the next working day.
04
Checking and acting on itConcept 04 · Check resource load in the same scenario as material
Material and Capacity in One Run
The shop-floor problem it solves
Materials are planned and bought, but the machines cannot make the order in time, so the shortage moves from the store to the shop floor.
The concept explained
A material plan says what to buy and make, not whether the plant has the hours to make it. With Enable resource scheduling switched on, Beas calculates the resources a scenario needs on top of its material requirements. This is MRP2. Requirement of resources MRP2 lists each resource with the hours from Forecasts, Sales order and Production against its Capacity, viewed by day, week or month. When the workload exceeds 90% of a resource's dispatching index, it is marked Overloaded, and Peggings Resources lists the peggings behind the load in the selected period. MRP2 is based on the lead time calculation, so Calculate lead time for assembly must be on and Forecast > Gross calculation off. The calculation takes longer.
Everyday analogy
Cooking for a family function. All the groceries are bought, but the kitchen has one stove with four burners. Unless someone also checks the burner hours, the sweets for sixty guests are not ready when the first guests arrive.
Where it lives in Beas
MRP > MRP Wizard > select a scenario > Resources opens Requirement of resources MRP2. Enable resource scheduling sits in Detail tab > Resources, and the Calculate resources column of the scenario list shows where it is active. Clicking a utilization bar opens the Origin of Requirement structure.
Swipe sideways to see the full diagramIllustrative figures: material and resource load from the same scenario; a week above 90% of the dispatching index is Overloaded.
05
Checking and acting on itConcept 05 · MRP proposes; the planner decides what becomes a request
Recommend, Then Decide
The shop-floor problem it solves
Either every proposal is turned into an order without a second look, or the list is ignored and buying goes back to spreadsheets.
The concept explained
The result of an MRP run is a recommendation, not a document. The Order recommendation shows, per item and period, the quantity to Buy, Make or Transfer, and the planner decides what happens next. Single mode is the default view. Massive mode works on all lines at once: Create request turns each line into a purchase request, a production request or an inventory transfer request, and Pre-Assign works out, for storage-related assemblies, what is needed for the next lead time plus buffer days. Production requests become work orders, and purchase requests become purchase orders. With Consider purchase and production requests on, open requests count as inflow in the next calculation; the option appears only when Purchase order and Request are activated under Purchase in the Detail tab.
Everyday analogy
A family member drafts the week's shopping list; the person running the kitchen strikes off what is not needed and only then places the order. Next week's list starts from what is now in the kitchen.
Where it lives in Beas
MRP > MRP Wizard > select a scenario > Order recommendation; the mode button switches to Massive mode. MRP > Production Request creates work orders as Individual orders, a Collective Order or Merge; Merge drops the link to the sales order, so use it for warehouse-related production only. Automatic calculation on the Scheduling tab runs the scenario through the Beas service planned activity “Calculate MRP”. Detail tab > Authorization sets Setup, View and Calculation rights per scenario.